| Project Name | Work Volume | Client | Owner/Location | Year |
|---|---|---|---|---|
| MLNG TA, ABF TA | HEAT TREATMENT WORKS | AMALGAMATED PLANT ENGINEERING SDN BHD | PETRONAS /MLNG BINTULU AND ASEAN BINTULU FERTILIZER SDN BHD | 2025 |
| ROSMARI MARJORAM FIELD DEVELOPMENT PROJECT | CAUSTIC TANK 1&2 T-1701 /1702 (TWO UNITS OF 7METER CARBON STEEL TANK) | EASTERN SOLDAR ENGINEERING & CONSTRUCTION SDN BHD | SHELL / BINTULU ,SARAWAK | 2025 |
| FUNACE HEAT FOR TANK SHELL PLATE | FURNACE HEATING | HUP CHUANG LEE (M) SDN BHD | DIALOG / TANJUNG LANGSAT , JOHOR | 2025 |
| MLNG TA | POST WELD HEAT TREATMENT, PRE-HEATING AND CONTROL BOLTING | HYPERWAVE SYSTEMS ENGINEERING SDN BHD | PETRONAS /MLNG BINTULU | 2025 |
| MALAKOFF PRAI POWER PLANT MAINTENANCE | POST WELD HEAT TREATMENT, PRE-HEATING, NDT AND WEDLING WORKS | MEERZA RESOURCES SDN BHD | MALAKOFF POWER BERHAD / PRAI, PENANG | 2025 |
| TO PROVIDE HEAT TREATMENT FOR V-8302 | POST WELD HEAT TREATMENT SERVICES | YU HOI CONSTRUCTION & ENGINEERING SDN BHD | JOHOR | 2025 |
| FURNACE HEAT FOR THE PIPE AND HOLLOW SECTIONS | FURNACE HEAT MORE THAN 1,000 METRIC TON | ADBON SERVICES SDN BHD | MERU,SELANGOR | 2024 |
| ROSMARI MARJORAM OGP PROJECT | POST WELD HEAT TREATMENT, PRE-HEATING AND HARDNESS TESTING. | EQUATOR ENGINEERING SDN. BHD. | SHELL /BINTULU ,SARAWAK. | 2024 |
| MLNG MAINTENANCE | POST WELD HEAT TREATMENT AND PRE-HEATING | HYPERWAVE SYSTEMS ENGINEERING SDN BHD | PETRONAS /MLNG BINTULU | 2024 |
| MLNG ROSMARI MARJORAM OGP | POST WELD HEAT TREATMENT AND CONTROL BOLTING | KPG ENGINEERING SDN BHD | PETRONAS & SHELL /MLNG BINTULU | 2024 |
| TANJUNG BIN POWER PLANT MAINTENANCE | POST WELD HEAT TREATMENT, PRE-HEATING, NDT AND WEDLING WORKS | MEERZA RESOURCES SDN BHD | MALAKOFF POWER BERHAD / TANJUNG BIN ,JOHOR | 2024 |
| SARAWAK METHANOL PLANT MAINTENANCE | HEAT TREATMENT FOR VALVE REPAIRING | SAMSUNG E&A MALAYSIA SDN BHD | SARAWAK PETCHAM / BINTULU ,SARAWAK | 2024 |
| MLNG MAINTENANCE | HEAT TREATMENT WORKS | AMALGAMATED PLANT ENGINEERING SDN BHD | PETRONAS /MLNG BINTULU | 2023 |
| TITANIUM NITRILE BUTADIENE LATEX OUTSIDE BATTERY LIMIT FACILITY PROJECT FOR PENGERANG INTEGRATED COMPLEX | HARDNESS TEST AND HEAT TREATMENT | DIALOG E&C SDN BHD | PETRONAS /PENGERANG INTEGRATED COMPLEX | 2023 |
| SARAWAK METHANOL PLANT | POST WELD HEAT TREATMENT, PRE-HEATING AND HARDNESS TESTING | EQUATOR ENGINEERING SDN. BHD. | SARAWAK PETCHEM / BINTULU ,SARAWAK. | 2023 |
| MLNG MAINTENANCE | POST WELD HEAT TREATMENT AND PRE-HEATING | HYPERWAVE SYSTEMS ENGINEERING SDN BHD | PETRONAS /MLNG BINTULU | 2023 |
| MAJUNG 4 POWER PLANT MAINTENANCE | POST WELD HEAT TREATMENT, PRE-HEATING, NDT AND WEDLING WORKS | MEERZA RESOURCES SDN BHD | TENAGA NASIONAL BERHAD (TNB) / MANJUNG,PERAK | 2023 |
| 8KM FIRE HYDRANT PIPELINE | 8KM FIRE HYDRANT PIPELINE 11K DIA INCH | BMECH ENGINEERING SDN BHD | PERTAMA FERROALLOYS SDN BHD / SAMALAJU,SARAWAK | 2022-2023 |
| SHELL SMDS BINTULU TA | POST WELD HEAT TREATMENT, PRE-HEATING, NDT, FLANGE MANAGEMENT, MECHANICAL AND WEDLING WORKS | PEC (M) SDN. BHD. | SHELL SARAWAK / BINTULU SARAWAK | 2022-2023 |
| PULAU INDAH POWER PLANT (PIPP) | POST WELD HEAT TREATMENT, PRE-HEATING AND HARDNESS TESTING | EQUATOR ENGINEERING SDN. BHD. | PULAU INDAH ,SELANGOR / WORLDWIDE AND KOREA ELECTRIC POWER (KEPCO). | 2022 |
| MLNG MAINTENANCE | POST WELD HEAT TREATMENT AND PRE-HEATING | HYPERWAVE SYSTEMS ENGINEERING SDN BHD | PETRONAS /MLNG BINTULU | 2022 |
| LOTTE CHEMICAL TITAN MAINTENANCE | POST WELD HEAT TREATMENT | LOTTE CHEMICAL TITAN (M) SDN BHD | LOTTE CHEMICAL TITAN MALAYSIA , JOHOR | 2022 |
| JIMAH POWER PLANT MAINTENANCE | POST WELD HEAT TREATMENT, PRE-HEATING, NDT AND WEDLING WORKS | P3 TECHNOLOGY ENGINEERING (KULIM) SDN BHD | TENAGA NASIONAL BERHAD (TNB) & MITSUI / PORT DICKSON ,NEGERI SEMBILAN | 2022 |
| PSR-2 TA 2022 PACKAGE 3 | POST WELD HEAT TREATMENT FOR VESSEL'S DISH HEAD 2 UNIS | PIONEER RANEX SDN BHD | PETRONAS / MELAKA ,MALAYSIA | 2022 |
| SMDS MAINTENANCE | POST WELD HEAT TREATMENT | RANEX (M) SDN BHD | SHELL /BINTULU ,SARAWAK | 2022 |
| RAPID MAINTENANCE | POST WELD HEAT TREATMENT | T??V RHEINLAND MALAYSIA SDN BHD | PETRONAS RAPID /PENGERANG ,JOHOR | 2022 |
| MLNG MAINTENANCE | HEAT TREATMENT WORKS | AMALGAMATED PLANT ENGINEERING SDN BHD | PETRONAS /MLNG BINTULU | 2021 |
| BASF PETRONAS MAINTENANCE | HARDNESS TEST AND HEAT TREATMENT | CHIRON PROBUILD SDN BHD | UPC CHEMICALS (M) SDN BHD /KUANTAN | 2021 |
| ABF MAINTENANCE | POST WELD HEAT TREATMENT AND PRE-HEATING | HYPERWAVE SYSTEMS ENGINEERING SDN BHD | PETRONAS /ASEAN BINTULU FERTILIZER SDN BHD | 2021 |
| TRACK 4B POWER PLANT MAINTENANCE | POST WELD HEAT TREATMENT | L.CHIN ENGINEERING SDN BHD | EDRA ENERGY | 2021 |
| MLNG MAINTENANCE | POST WELD HEAT TREATMENT AND PRE-HEATING | MAYSVILLE SENDIRIAN BERHAD | PETRONAS /MLNG BINTULU | 2021 |
| MAJUNG POWER PLANT MAINTENANCE | POST WELD HEAT TREATMENT, PRE-HEATING, NDT AND WEDLING WORKS | MEERZA RESOURCES SDN BHD | TENAGA NASIONAL BERHAD (TNB) / MANJUNG,PERAK | 2021 |
| TANJUNG BIN POWER PLANT MAINTENANCE | POST WELD HEAT TREATMENT, PRE-HEATING, NDT AND WEDLING WORKS | P3 TECHNOLOGY ENGINEERING (KULIM) SDN BHD | MALAKOFF POWER BERHAD / TANJUNG BIN ,JOHOR | 2021 |
| LOTTE CHEMICAL TITAN STORAGE TANKS | FURNACE HEAT FOR THE TANK SHELL PLATE | TONG SENG FABRICATORS SDN BHD | LOTTE CHEMICAL TITAN MALAYSIA / PASIR GUDANG , JOHOR | 2021 |
| TRACK 4A 1440 MW CCGT POWER PLANT | JOINT INTEGRITY TEAM AND HYDROTEST | EQUATOR ENGINEERING SDN BHD | SOUTHERN POWER GENERATION PENGARANG JOHOR | 2020 |
| PACKAGE 14 | JOINT INTEGRITY TEAM AND HYDROTEST | OUI JV | PETRONAS PENGARANG JOHOR | 2020 |
| PETRONAS PENAPISAN MELAKA MAINTENANCE | HEAT TREATMENT WORKS | DIALOG PLANT SERVICES SDN. BHD. | PETRONAS /MLNG BINTULU | 2020 |
| TANJUNG KIDURONG COMBINED CYCLE POWER PLANT (CCGT) | POST WELD HEAT TREATMENT AND PRE-HEATING | EAST GAS SDN BHD | SARAWAK ENERGY / BINTULU SARAWAK | 2020 |
| RAPID MAINTENACE WORKS | POST WELD HEAT TREATMENT AND PRE-HEATING | ENPROSERVE (M) SDN BHD | RAPID PENGERANG | 2020 |
| 1.44 GW COMBINED CYCLE GAS POWER PLANT | POST WELD HEAT TREATMENT, PRE-HEATING AND HARDNESS TESTING | EQUATOR ENGINEERING SDN. BHD. | PASIR GUDANG ,JOHOR / SOUTHERN POWER GENERATION | 2020 |
| FUNACE HEAT FOR TANK SHELL PLATE | FURNACE HEATING | HUP CHUANG LEE (M) SDN BHD | DIALOG / PENGERANG , JOHOR | 2020 |
| EURO 5 PROJECT MELACCA | POST WELD HEAT TREATMENT | KPG ENGINEERING SDN BHD | PETRONAS / SUNGAI UDANG ,MELAKA | 2020 |
| RAPID PACKAGE 1 SHUT DOWN MAINTENANCE | POST WELD HEAT TREATMENT AND HARDNESS TESTING | VORPLEX GROUP SDN BHD | PETRONAS RAPID /PENGERANG ,JOHOR | 2020 |
| SAMUR PROJECT | HYDRAULIC CONTROLLED BOLTING (TORQUE/TENSIONING) | MITSUBISHI HEAVY INDUSTRIES LTD. | SABAH | 2019 |
| TRAIN9 MRU PROJECT | POST WELD HEAT TREATMENT | JGC (M) SDN BHD | BINTULU | 2019 |
| SMDS SHUTDOWN | PREHEATING AND POST WELD HEAT TREATMENT | PEC (M) SDN BHD | BINTULU | 2019 |
| MELAKA SHUTDOWN | PREHEATING, POST WELD HEAT TREATMENT, POST HEATING & HADNESS TEST | DIALOG PLANT SERVIES SDN BHD | MELAKA | 2019 |
| PSR-2 TURNAROUND PLANT CHANGE PROJECT | PREHEATING, POST WELD HEAT TREATMENT, & HADNESS TEST | DIALOG PLANT SERVIES SDN BHD | MELAKA | 2019 |
| PCP PENGERANG COGENERATION PLANT PROJECT | POST WELD HEAT TREATMENT & PREHEATING & HARDNESS TEST (TURBINE) | IAQ SOLUTION SDN BHD | PETRONAS PENGERANG JOHOR | 2018 |
| PCP PENGERANG COGENERATION PLANT PROJECT | POST WELD HEAT TREATMENT & PREHEATING & HARDNESS TEST (EST. 31,000 DIA INCH BOILER) | EQUATOR ENGINEERING SDN BHD | PETRONAS PENGERANG JOHOR | 2018 |
| PENGERANG 1220MW COGENERATION PLANT PROJECT | POST WELD HEAT TREATMENT, PREHEATING & HARDNESS TEST & POST HEATING | EQUATOR ENGINEERING SDN BHD | PENGARANG JOHOR | 2018 |
| JIMAH EAST POWER PLANT PROJECT | PREHEATING & POST WELD HEAT TREATMENT | EQUATOR ENGINEERING SDN BHD | TANJONG SEPAT NEGERI SEMBILAN | 2018 |
| TECHICAS REUNIDAS RAPID PACKAGE | POST WELD HEAT TREATMENT, HARDNESS TEST, PREHEATING & POST HEATING | EQUATOR ENGINEERING SDN BHD | PENGARANG JOHOR | 2018 |
| PENGARANG RAPID SCC PROJECT | POST WELD HEAT TREATMENT & PREHEATING | EQUATOR ENGINEERING SDN BHD | PENGARANG JOHOR | 2018 |
| PROVISION OF MAIN MECHANICAL WORKS FOR FSR-2 & MG3 TA2015/16 AT PPMSB | POST WELD HEAT TREATMENT | PETRONAS PENAPISAN MELAKA | MELAKA | 2018 |
| PACKAGE 5 RAPID PROJECT | PREHEATING & POST WELD HEAT TREATMENT | SINO PETROCHEMICAL CONSTRUCTION SDN BHD | PENGARANG JOHOR | 2018 |
| PACKAGE 14 RAPID PROJECT | PREHEATING, POST WELD HEAT TREATMENT, POST HEATING & HADNESS TEST | CPP PETROLEUM ENGINEERING (M) SDN BHD | PENGARANG JOHOR | 2018 |
| PETRONAS RAPID PROJECT | POST WELD HEAT TREATMENT | SINO TCC (M) SDN BHD | PENGARANG JOHOR | 2018 |
| RAID TOYO | PREHEATING & POST WELD HEAT TREATMENT & HARDNESS TEST (EST. 18,000 DIA INCH) | DIALOG FABRICATION SDN BHD | PETRONAS PENGERANG JOHOR | 2017 |
| PROVISION OF EPCC DELTA VALUE TUB AT DCU COKE DRUM | PREHEATING & POST WELD HEAT TREATMENT | DIALOG PLANT SERVIES SDN BHD | MELAKA | 2017 |
| PLANT CHANGE WORK | PREHEATING, POST WELD HEAT TREATMENT & HARDNESS TEST | KPG ENGINEERING SDN BHD | MLNG BINTULU | 2017 |
| RAPID PROJECT | 5,000 DIA INCH POST WELD HEAT TREATMENT & HARDNESS TEST | DIALOG FABRICATOR SDN BHD | PENGARANG JOHOR | 2017 |
| RAPID RGT-2 TERMINAL PROJECT | PREHEATING & POST WELD HEAT TREATMENT | DIALOG FABRICATOR SDN BHD | PENGARANG JOHOR | 2017 |
| PENGARANG JOHOR | POST WELD HEAT TREATMENT, PREHEATING & HARDNESS TEST & CONTROLLED BOLTING | MHI ENERGY & ENVIRONMENT (M) SDN BHD | SIPITANG SABAH | 2017 |
| RAPID PROJECT (ELECO) | PREHEATING & POST WELD HEAT TREATMENT | KOSTEC NDT CONSULTANCY SDN BHD | PENGARANG JOHOR | 2017 |
| PETRONAS RAPID PROJECT | PREHEATING & POST WELD HEAT TREATMENT | SINO TCC (M) SDN BHD | PENGARANG JOHOR | 2017 |
| PETRONAS RAPID PROJECT | HARDNESS TEST | SINO TCC (M) SDN BHD | PENGARANG JOHOR | 2017 |
| TANK 7 | HYDRAULIC CONTROLLED BOLTING (TORQUE) | TKM / BPMECH | MLNG | 2017 |
| TURAROUND PSR 2 | POST WELD HEAT TREATMENT TEAM SUPPLY 5 TEAMS | DIALOG PLANT SERVICE SDN BHD | PETRONAS | 2016 |
| NEW VESSEL | POST WELD HEAT TREATMENT | ENCO SYSTEMS SDN BHD | RAWANG | 2016 |
| MANJUNG 5 COAL FIRE 1X1000MW | 23,000 DIA INCH(FIELD WORK) PREHEATING & POST WELD HEAT TREATMENT | EQUATOR ENF. SDN BHD | TNB MANJUNG | 2016 |
| TGAST PROJECT | POST WELD HEAT TREATMENT 31,000 DIA INCH WORKSHOP & FIELD | EVERSENDAI OIL & GAS SDN BHD | PETRONAS TERENGGANU | 2016 |
| SHELL PLATE | 100 PCS FURNACE HEAT | ICE PETROLEUM ENG. SDN BHD | PETRONAS PENGERANG JOHOR | 2016 |
| POST CURING AND CLEANING | POST WELD HEAT TREATMENT | DIALOG PACIFIC ADVANCE COMPOSITES SDN BHD | NILAI NEGERI SEMBILAN | 2016 |
| TERENGGANU GAS TERMINAL PROJECT | 49,929 DIA INCH | EVERSENDAI OIL AND GAS SDN BHD | KERTEH TERENGGANU | 2016 |
| MRU PROJECT | POST WELD HEAT TREATMENT | DIALOG FABRICATOR SDN BHD | PENGARANG JOHOR | 2016 |
| MANJUNG 5 POWER PLANT | PREHEATING, POST WELD HEAT TREATMENT & HARDNESS TEST & POST HEATING | EQUATOR ENGINEERING SDN BHD | MANJUNG PERAK | 2016 |
| PENGARANG RAPID PROJECT | POST WELD HEAT TREATMENT | KOSTEC NDT CONSULTANCY SDN BHD | PENGARANG RAPID PROJECT | 2016 |
| TRAIN 9 PRE-FABRICATION ON PIPING PROJECT | POST WELD HEAT TREATMENT 51,000 DIA INCH FEB | DIALOG/ JGC | BANTING SELANGOR | 2015 |
| FMC-SHELL PRELUDE WORKSHOP FABRICATION | PREHEATING WORKS | FMC WELLHEAD EQUIPMENT SDN BHD | KENCANA TORSCO WORKSHOP MANJUNG PERAK | 2015 |
| THE PROVISION OF EPCC FOR ONSHORE SLUGCATCHER(OSC) BLENDING FACILITIES OF TGAST-OSC-GPPA(TOG) MODIFICATION FOR PETRONAS CARIGALI SDN BHD | POST WELD HEAT TREATMENT & HARDNESS TEST WORKS | KQKS ENG. & CONS. SDN BHD | KERTEH TERENGGANU | 2015 |
| TRAIN 9 SITE ELECTION POST WELD HEAT TREATMENT WORK ON PIPING | POST WELD HEAT TREATMENT WORKS (EST. 20,000 DIA INCH) | PEC ENGINEERING SDN BHD | BINTULU SARAWAK | 2015 |
| SAMUR PROJECT | POST WELD HEAT TREATMENT TEAM SUPPLY | MITSUBISHI HEAVY INDUSTRIES | PETRONAS | 2015 |
| T9 GMS | HYDRAULIC CONTROLLED BOLTING (TORQUE/TENSIONING) | JGC / SYNERLITZ | MLNG | 2015 |
| MNB BOILER PROJECT | PREHEATING AND POST WELD HEAT TREATMENT P11 ALLOY - 10,000 DIA INCH | SNC/ MLNG | MLNG BINTULU | 2014 |
| FABRICATION OF STORAGE TANKS IN PIT 101 & 103 | FURNACE HEAT FOR TANK PLATE X 126 PCS | EASTERN SOLDAR/ DIALOG | PENGARANG JOHOR WORKSHOP | 2014 |
| DGDM PROJECT | POST WELD HEAT TREATMENT FOR PIPING(36?€? PIPE 34MM THICK) 14,000 DB | AQEEL SDN BHD | MLNG BINTULU | 2014 |
| MANJUNG 4X100 COAL FIRE POWER PLANT | PREHEATING & POST WELD HEAT TREATMENT 10,000 DIA INCH | EESB/ TNB | MANJUNG POWER PLANT | 2014 |
| FABRICATION OF STORAGE TANKS | FURNACE HEAT FOR TANK SHELL PLATE X 106 PCS | CHINA CO./ DIALOG | PENGARANG JOHOR | 2014 |
| PDR M04-EPCC OF TWO CRUDE & TWO BITUMEN TANK PROJECT AT NEW LAND | FURNACE HEAT FOR TANK SHELL PLATE X 28 PCS | EASTERN SOLDAR ENG. CONS. S/B | SEREMBAN NEGERI SEMBILAN | 2014 |
| MARLIN PROJECT | POST WELD HEAT TREATMENT ON PIPING | PEC ENGINEERING SND BHD | BINTULU SARAWAK | 2014 |
| SOGT KIMANIS | 25,000 DIA INCH | EPIC MUSHTARI SDN BHD | KIMANIS SABAH | 2012 |
| KPOC | PREHEATING & POST WELD HEAT TREATMENT WORK FOR 13 TONS JACKET | KENCANA HL | LUMUT YARD | 2012 |
| E8K COMPRESSION MODULE | PREHEATING POST WELD HEAT TREATMENT FOR TOPSIDE | KENCANA HL | LUMUT YARD | 2012 |
| F13K COMPRESSION MODULE | PREHEATING & POST WELD HEAT TREATMENT FOR TOPSIDE | KENCANA HL | LUMUT YARD | 2012 |
| GARRAF FIELD DEVELOPMENT | POST WELD HEAT TREATMENT WORK FOR PIPING | KENCANA TORSCO | LUMUT YARD | 2012 |
| WEST DESARUMOPU EXTENSION PROJECT | PREHEATING & POST HEAT FOR LEG EXTRENSION | KENCANA HL | LUMUT YARD | 2012 |
| 4TH DRIER BED PROJECT | POST WELD HEAT TREATMENT FOR PIPING (3000 DB) | KQKS SDN BHD | MLNG BINTULU | 2012 |
| PSR2 TURN AROUND 2011 | PIPING AND VESSEL POST WELD HEAT TREATMENT 30 TEAMS | DIALOG PLANT SERVICE SDN BHD | PETRONAS MELAKA SUNGAI U DANG | 2011 |
| ABF REVAMP PROJECT | 80 LINE X 10 JOINTS | DIALOG E&C SDN BHD | ABF BINTULU | 2011 |
| METHANOL 1 REVAMP PROJECT | 3 TEAMS | DIALOG PLANT SERVICE S/B | LABUAN W/P MALAYSIA | 2010 |
| PSR 2 REVAMP PETRONAS MELAKA | 2 TO 4 TEAMS | DIALOG E&C SDN BHD | PETRONAS MELAKA SUNGAI U DANG | 2010 |
| PSR 2 REVAMP PETRONAS MELAKA | 2 TO 4 TEAMS | PFCE SDN BHD/ SHAMIRA SDN BHD | PETRONAS MELAKA SUNGAI U DANG | 2010 |
| PP(MELAKA) SB PSR2 REVAMP | PIPING POST WELD HEAT TREATMENT 25,000 DB | WONG HENG ENGINEERING SDN BHD | MALAKA | 2009 |
| MLNG 5&6 REVAMP | PIPING POST WELD HEAT TREATMENT 10,000 DB | ALMAGAMATED PLANT ENGINEERING S/B | BINTULU SARAWAK MALAYSIA | 2009 |
| ASIA PETROLEUM HUB | FURNACE POST WELD HEAT TREATMENT FOR SHELL PLATE WITH CLEAN OUT DOOR | TORSCO OVERSEAS SDN BHD */ KENCANA INFLA | LUMUT SITIAWAN PERAK | 2009 |
| BOKOR REDEVELOPMENT PROJECT PHASE 2 | PIPING POST WELD HEAT TREATMENT SHOP AND HOOK UP | VASTALUX SDN BHD | MIRI OFFSHORE | 2009 |
| PC-4 HUP | HOOK UP | TOTAL STERLING/ DAYANG | MIRI OFFSHORE | 2009 |
| MAARI FIELD DEVELOPMENT WELLHEAD PLATFORM PROJECT | PREHEATING FOR HEAVY STRUCTURE & PIPING POST WELD HEAT TREATMENT 15 TEMAS | KENCANA HL | LUMUT SITIAWAN PERAK | 2008 |
| HEERA REDEVPMENT PROJECT | FURNACE POST WELD HEAT TREATMENT FOR TUBULAR | KENCAN HL | LUMUT SITIAWAN PERAK | 2008 |
| PP(MELAKA) SB MG3 | PIPING POST WELD HEAT TREATMENT 70,000 DB | KQKS | MELAKA | 2008 |
| METHANOL EXPENSION | PIPING POST WELD HEAT TREATMENT 70,000 DB | SHAMIRA/ DIALOG E&C SDN BHD | LABUAN MALAYSIA | 2008 |
| HEERA REDEVPMENT PROJECT | PREHEATING & POST WELD HEAT TREATMENT FOR HEAVY STRUCTURE & PIPNG POST WELD HEAT TREATMENT 4 JACKET & 4 TOPSIDE | KENCANA HL | LUMUT SITIAWAN PERAK | 2008 |
| J4 PROJECT | PREHEATING FOR HEAVY STRUCTURE & PIPNG POST WELD HEAT TREATMENT | KENCANA HL | LUMUT SITIAWAN PERAK | 2008 |
| MULLUT BASIN | PIPING 4 TEAMS | PEREMBA PECD | PETRODAR/ SUDAN ARFICA | 2007 |
| CTOC BROWN FIELD | PIPING POST WELD HEAT TREATMENT 6,000 DB | KENCANA HL | LUMUT | 2007 |
| CTOC BROWN FIELD | PIPING POST WELD HEAT TREATMENT 8,000 DB | MUSHTARI ENG. AND TRADING | KEMAMAN TERENGGANU | 2007 |
| CTOC BROWN FIELD | OFFSHORE ERECTION POST WELD HEAT TREATMENT WORKS 2 TEAMS | MUSHTARI ENG. AND TRADING | OFFSHORE KELANTAN | 2007 |
| BCP-B2 (INDIA PROJECT) | POST WELD HEAT TREATMENT & PREHEATING | KENCANA HL | LUMUT SITIAWAN PERAK | 2007 |
| TANJUNG BIN 3 X 700 MW POWER STATION | 10,000 DIA INCH | VANTAGE STEEL WORKS SDN BHD | TANJUNG BIN, JOHOR | 2006 |
| TUAN JAAFAR POWER STATION | 20,000 DIA INCH | EQAUTOR ENGINEERING SDN BHD | PORT DICKSON | 2004 |
| MULLUT BASIN | LOCALISED 100 NOS 10?€? TO 36?€? NOZZLE & MAIN HOLE FOR TANK | WHESSOE SDN BHD | PETRODAR/ SUDAN AFRICA | 2004 |
| SMDS DEBOLTLE NECKING | 4,000 DIA INCH | HAVESTECH ENGINEERING SDN BHD | SMDS BINTULU | 2003 |
| PSR2 SHUTDOWN | 4,000 DIA INCH | WONG HENG ENGINEERING SDN BHD | MALAKA | 2003 |
| MANJUNG POWER STATION X 700 MW | 40,000 DIA INCH | EVERSENDAINEIE POWER SDN BHD | TNB | 2002 |
| MLNG TIGA | 8,000 DIA INCH | WONG HENG ENG. SDN BHD | PETRONAS MLNG BINTULU | 2002 |
| PANLIMA POWER STATION | 7,000 DIA INCH | CTCI/ YONGHAN SDN BHD | POWERTECH MELAKA | 2002 |
| PANLIMA POWER STATION | SUPPLY 6 TEAMS | SUKWON IDCHE ENG. SDN BHD | POWERTECH MELAKA | 2002 |
| OPTIMA MALAYSIA | 9,000 DIA INCH | SUKWON INCHE SDN BHD | OPTIMA MALAYSIA KERTEH | 2001 |
| OPTIMA MALAYSIA | 4,500 DIA INCH | SANDOH ENG. | OPTIMA MALAYSIA KERTEH | 2001 |
| OPTIMA MALAYSIA | 5,000 DIA INCH | HL ENG. SDN BHD | OPTIMA MALAYSIA KERTEH | 2001 |
| PETRONAS AMMONIA SYNGAS | 50,000 DIA INCH | SUMATEC CO. | PETRONAS KERTEH | 2000 |
| SHELL MDS RECONSTN BINTULU | 23,000 DIA INCH | HARVEST ECH SINBERY JV S/B | SHELL MDS BINTULU SARAWAK | 1999 |
| SHELL MDS RECONSTN BINTULU | 5,500 DIA INCH | PLANT ENGINEERING CO (PEC) | SHELL MDS BINTULU SARAWAK | 1999 |
| PSR 2 MELAKA | 20,000 DB | JEMIX/ CHIYODA | PETRONAS REFINERY | 1998 |
| MENTAKAB ABB POWER STATION | 20,000 DB | SIKOJAYA | ABB POWER JANERATION | 1998 |
| SHELL LRCC PORT DICKSON | 900 BENDS HFIB SPOOL | JGC | SHELL REFINERY P.DICKSON | 1998 |
| ELP OP PLANT BRUNEI | 15,000 DB | 1,500 JTS | SKS/ TECHNIP FAR EAST | ELF ONSHORE PRODUCTION PLANT BRUNEI | 1998 |
| SHELL LRCC PORT DICKSON | CHANGE ORDER 5,500 JTS (SHOP) | JGC | SHELL REFINERY PORT DICKSON | 1998 |
| SHELL LRCC PORT DICKSON | CHANGE ORDER 7,800 JTS (FIELD) | JGC | SHELL REFINERY PORT DICKSON | 1998 |
| HEATER COIL FOR OVERSEA PROJECT | 13,000 DB | 2,500 JTS | STEELCON SDN BHD | BORN HEATER | 1997 |
| TIONG A INFILL DRILLING PIPING POST WELD HEAT TREATMENT | 700 DB | VEROSI SDN BHD | PCSB | 1997 |
| STAR PETROLEUM REFINERY PROJECT(THAILAND) | 212,000 DB | 75,000 JTS | JEMIX/ JGC | STAR PETROLEUM REFINERY CO. | 1996 |
| SHELL REFINERY SHUT DOWN PIPING POST WELD HEAT TREATMENT & PREHEAT | 600 DB | ITI | SHELL REFINERY DICKSON | 1994 |
| APS MODENIZATION PIPING POST WELD HEAT TREATMENT | 1,100 DB | WONG HENG ENG/ JGC | ESSO REFINERY DICKSON | 1994 |
| SMDS MODIFICATION PIPING POST WELD HEAT TREATMENT | 600 DB | TIAN SAN/ JGC | SHELL MDS | 1993 |
| SMDS PPING POST WELD HEAT TREATMENT | 90,000 DB | 15,000 JTS | JEMIX/ HYUNDAY/ JGC | SHELL MDS | 1992 |
| SMDS LNG TIE IN PIPING POST WELD HEAT TREATMENT | 5,000 DB | JEMIX/ TIAN SAN/ JGC | SHELL MDS | 1992 |
| TUB-01 PIPING POST WELD HEAT TREATMENT | 700 DB | MUSHTARI | EPMI | 1992 |